Project |
Type |
Amount
(ton) |
Delivery
date |
Owner |
|
bazhou-wuzhuang |
LGJ-400/35 |
317.97t |
03.04.15 |
North China Grid Company Limited |
|
433.29t |
03.04.15 |
North China Grid Company Limited |
|
ningbo-wenzhou |
LGJX-630/45 |
1700t |
03.03.15 |
Zhejiang Electric Power Company |
|
nanchang-lewan |
LGJ-400/35 |
939.061t |
03.06.20 |
State Grid Corporation of China |
|
Dalate electricity works-yongshengyu |
LGJ-400/35 |
533.329t |
03.05.10 |
Neimenggu Electric Power Company |
|
Huizhou earthing |
LGJ-630/45 |
385.393t |
03.04.10 |
State Grid Corporation of China |
|
Jingzhou earthing |
LGJ-630/45 |
170.45t |
03.04.10 |
State Grid Corporation of China |
|
Shentou electricity works-north baoding |
LGJ-400/35 |
1227.5t |
03.06 |
North China Grid Company Limited |
|
jinmen-xiaogan |
LGJ-500/45 |
566.132t |
03.06.05 |
State Grid Corporation of China |
|
Dalate electricity works-wuhai |
LGJ-400/35 |
552.62t |
03.08.01 |
Neimenggu Electric Power Company |
|
Yancheng - yangzhou |
LGJ-630/45 |
4683.3t |
03.08 |
Jiangsu Electric Power Company |
|
Chefang - wuxi southeast |
LGJ-630/45 |
1400.8t |
03.09 |
Jiangsu Electric Power Company |
|
Guizhou - guangdong |
ACSR-720/50 |
3485.607t |
03.07 |
China Southern Power Gird |
|
baoding project |
LGJ-400/35 |
959.5t |
03.10.01 |
Hebei Electric Power Company |
|
Angezhuang - binhai |
JL/LB1A-400/35 |
827.7t |
03.12 |
North China Grid Company Limited |
|
Hunyuan-Bazhou |
LGJ-300/40 |
2760.11t |
04.03.10 |
North China Grid Company Limited |
|
Jiangsu project |
LGJ-400/35 |
3871.63t |
04.06 |
Jiangsu Electric Power Company |
|
Luohe electricity works -Chuzhou |
LGJ-400/35 |
715.884t |
04.09 |
East China Grid Company Limited |
|
Longtan-Dongshanqiao |
LGJ-400/35 |
1468.526t |
04.09 |
Jiangsu Electric Power Company |
|
Tongbo-Zhuji |
LGJ-630/45 |
1059t |
04.10 |
Zhejiang Electric Power Company |
|
Yiwu-Jinhua、Qiangjiao-Ninghai、Ouhai-Wennan |
LGJ-400/35 |
1295t |
04.10-12 |
Zhejiang Electric Power Company |
|
Tianshengqiao-Guangdong |
LGJ-400/35 |
930.933t |
04.11-12 |
China Southern Power Gird |
|
Fanchang~xuancheng |
LGJ-400/35 |
1205.23 t |
05.01 |
East China Grid Company Limited |
|
Hangzhou-taizhou-wenzhou |
LGJ-630/45 |
3226t |
05.02 |
Zhejiang Electric Power Company |
|
huaneng electricity works-Taichang |
LGJ-630/45 |
3859t |
05.07-10 |
Jiangsu Electric Power Company |
|
Wangquan-shunyi |
LGJ-400/35 |
1296.1t |
05.05-07 |
North China Grid Company Limited |
|
Tai’an-Ji’ning |
LGJ-400/35 |
2232.83t |
05.04-06 |
Shandong Electric Power Company |
|
Gaoxing-Buridu |
LGJ-400/35 |
1016.53t |
05.04.25 |
Neimenggu Electric Power Company |
|
500kV Huangjinbo Power Plant-Yingtan-Leping |
LGJ-400/35
|
2035.968t |
06.03.16 |
Jiangsxi Electric Power Corporation |
|
500kV Liaoning Dianbo Line |
JL/LB20A-400/35 |
1143.8t |
06.05.12 |
Yingkou Power Supply Company |
|
JL/LB20A-400/50 |
68.46t |
|
500kV Sanbao-Jiangbei |
Bittern
|
4222t |
06.06.13 |
Jiangsu Hengyuan Power Materials Company |
|
500kV Chuzhou-Ma’an Zhankou |
LGJ-630/45
|
3141.5t |
06.08.24 |
Shanghai East-China Power Materials Union Company |
|
Lianzhou-Cangxi500kV Line |
LGJ-400/35
|
417.41t |
06.10.17 |
Herbei Electric Power Corporation |
|
500kV Guiguang Erhui |
Bobolink |
2957.4t |
06.07.18 |
China Southern Grid Company |
|
500kV Longtan Water and Electricity |
LGJ-400/35 |
886.3t |
06.07.18 |
China Southern Grid Company |
|
500kV Fengzhen~Hanhai |
LGJ-400/35 |
1022.82t |
06.07.20 |
Inner Mongolia Super-high Voltage Power Supply Bureau |
|
500kV Huaibeng Line |
LGJ-630/45 |
2245.4t |
06.10.19 |
Anhui Wandian Materials Company |
|
500kVa Huolinhe~Tongliao~Shaling |
LGJ-300/40 |
2164.353t |
06.11.22 |
Northeast Electricity Management Bureau |
|
500kV Qunsui Line |
LGJ-300/40 |
5520t |
06.08.31 |
Heilongjiang Power Development Construction Group |
|
500kV Linhai~Yiwu |
LGJ-630/45 |
2360t |
06.11.23 |
Zhejiang Power Company |
|
500kV Liu’an-Tonggui |
LGJ-630/45 |
4250t |
07.04.18 |
East-China Power Foreign Trade Company |
|
LGJ-95/55 |
23.963t |
|
Shuiboya-Caijiachong 500kV Line Project |
LGJ-630/55 |
2283.5t |
07.05.27 |
Wuhan buhua Trade Company |
|
LGJ-500/45 |
2323.6t |
|
Shi’en—Shuibuya Sanhui 500kV Line |
LGJ-400/35 |
1324.26t |
07.07 |
Wuhan buhua Trade Company |
|
Drake |
1161.364t |
|
Ping Dingshan—Luonan 500kV Line |
LGJ-630/45 |
2502.949t |
07.07 |
Wuhan buhua Trade Company |
|
500kV Wuhu Power Plant-Ma’an Shan Line |
LGJ-630/45 |
3500t |
07.814 |
East-China Power Foreign Trade Company |
|
500kV Maxi Line-Eat-China |
LGJ-630/45 |
1700t |
07.09.14 |
East-China Power Foreign Trade Company |
|
500kV Wangdian-Jiashanbian Line |
LGJ-630/45 |
1586.43t |
07.10.30 |
East-China Power Foreign Trade Company |
|
LGJ-400/35 |
7.28t |
|
LGJ-95/55 |
27.22t |
|
500kV Benwang Line Project |
LGJ-630/45 |
2227t |
07.10.29 |
Liaoning Benxi Power Supply Company |
|
1000kV Jindongnan-Nanyang-Jinmen Super-high Voltage A.C Test Project |
LGJ-500/35 |
2822t |
07.07 |
State Grid Corporation |
|
500kV Sanguandian-East Nantong Line |
LGJ-630/45 |
1192.885t |
08.01 |
Jiangsu Power Materials Company |
|
Diannan Waisong Channel 500kV Project |
LGJ-300/40 |
1741.1t |
07.12 |
China Southern Grid Company |
|
E’Gan Sanhui 500kV Line |
LGJ-400/50 |
517.851t |
08.01 |
Wuhan buhua Trade Company |
|
LGJ-400/35 |
497.247t |
|
LGJ-400/35 |
964.449t |
|
LGJ-400/35 |
77.783t |
|
500kV Ma’anshan No.3 Power Plant Project |
LGJ-630/45 |
1030t |
08.02 |
Shanghai East-China Power Materials Union Company |
|
LGJ-400/35 |
78t |
|
500kV Guangyuan-Mianyang Line |
LGJ-400/35 |
1953.309t |
08.03 |
Sichuan Power Company |
|
Tapu-Xiangfu-Xuchang-Shaoling 500kV Line |
LGJ-400/35 |
701.6t |
08.07 |
Wuhan buhua Trade Company |
|
LGJ-400/35 |
518.4t |
|
LGJ-400/50 |
18.9t |
|
Wuhai-North Wuhai 500kV Line Project |
LGJ-400/35 |
405.97t |
08.07 |
Inner Mongolia Super-high Voltage Power Supply Bureau |
|
750kV Weinan-Kunxian County Line |
Drake |
1650t |
08.09 |
Shaanxi Power Materials Company |
|
500kV Guancheng-Shaobei Shuanghui Line |
JL/LB1A-630-45/7 |
4857.6t |
08.10 |
Zhejiang Power Company |
|
750kV Binchang Power Plant-Ganxian County Line |
LGJK-400/45 |
1775.76t |
08.10 |
Shaanxi Power Materials Company |
|
Cangdong-Banqiao 500kV Line |
JL/LB20A-400/35 |
1472.35t |
08.11 |
North-China Power Materials Headquarters |
|
Beijing Mentougou 500kV Line |
LGJ-240/30 |
778t |
08.11 |
North-China Materials Headquarters |
|
TOTLE |
114464t |
|
|